2017 Water Line Improvements

Project Description


A number of water line improvement projects will occur in 2017 to address capacity issues and deteriorated lines. Those include replacing approximately 700 feet of water line on Sunset Lane; constructing approximately 1,500 feet of water main to connect the Berkshire Circle and North Wyndham Heights Drive neighborhoods and improve water pressures; and constructing water main along Grand Mere Parkway. Only the Sunset Lane project will have traffic impacts to the neighborhood.

Budget


  • $155,000 for Sunset Lane water improvements
  • $75,000 for Berkshire Circle water improvements

Timeline


Anticipated award of bid April 18
Construction timeline May-November 2017