Project Description


The 2014, the Kansas Department of Transportation (KDOT) awarded a safety grant to the City for intersection improvements at College Avenue and Claflin Road. The project involves adding a new traffic signal on the south leg of the intersection for the addition of a protected left phase. The existing configuration of this intersection has a shared left and thru phase for southbound traffic.

Budget


KDOT's maximum participation is capped at $100,000. The City will be responsible for approximately $30,000.


Timeline


 Anticipated bid letting by KDOT January 2017
 Anticipated City Commission concurrence February 2017
 Construction Timeline TBD