College Heights & Quivera Storm Sewer Project

Project Description


Collapsed storm sewer under College Heights Road will be replaced, and storm inlets will be added on Quivera Circle to improve drainage in the area. Josh Connet Excavation will be the contractor on this project.

Traffic Impact


The intersection of College Heights and Quivera will be closed from June 1 through early September for this construction work. A detour will be in place, and motorists should use caution with the nearby Denison Avenue water line project detour also in place.

Project Update, Aug. 1


Crews have completed the relocation of gas, sanitary sewer and water utilities. Installation of the new inlets and drainage pipe is underway, and street paving will be completed shortly after the work beneath the roadway is finished. Construction is running two to three weeks behind schedule, but pavement placement is expected to begin the last week of August.

Budget


  • Total construction costs of $229,784.58 will be paid from the Stormwater Fund

Timeline


Award of bid May 16
Construction timeline June 1-Aug. 16